Contract PC-95-FSH

Impala Platinum • Platinum Ore

All Contracts Edit Contract

0.0%

Progress

0

Tons Delivered

15,000

Tons Remaining

Active

Status

Contract Information
Contract Code PC-95-FSH Client Impala Platinum
Product Platinum Ore Grade N/A
Target Quantity 15,000.000 tons Price per Ton R15,000.00
Currency ZAR Incoterms FOB
Start Date Apr 15, 2025 End Date Oct 15, 2025
Created Aug 26, 2025 21:57 Last Updated Never
Notes Platinum ore contract
Delivery Progress
Target Quantity 15,000.000 tons Delivered 0.000 tons
Remaining 15,000.000 tons Progress
0.0%
Contract Value R225,000,000.00 Value Delivered R0.00
Recent Dispatches (Last 10)
Dispatch # PC Number Transporter Truck Driver Tonnage Status Date
DISP-2025-018 PC-95-FSH N/A N/A N/A 35.0t Planned Aug 26, 21:57